towers

Schedules and Timelines

Updates

Current Timeline of Events regarding Yucca Mountain

 

New issued schedule as of
July 21st, 2009

On July 10, 2009, the NRC Staff responded to the Board’s July 2, 2009 order concerning scheduling. The Staff stated that it will not be able to issue its Safety Evaluation Report (SER) in accordance with the schedule in 10 C.F.R. Part 2, Appendix D. Rather, at present, the Staff intends to issue the SER serially. The Staff estimates that the SER will be issued as follows:

Volume 1 of General Information

March 2010
Volume 3 (Review of Repository Safety After Permanent Closure)
September 2010

The Staff asserts that completion dates for three other volumes 2, 4 and 5 cannot be estimated with a reasonable degree of certainty at this time. In the absence of a Staff estimate, unless and until informed to the contrary, the Board will assume solely for case management purposes that these volumes will be issued approximately as follows:

Volume 2 (Review of Repository Safety Before Permanent Closure);

(October 2011)

Volume 4 (Review of Administrative and Programmatic Requirements);

(December 2010)

and Volume 5 (License Specifications and Conditions)

(February 2012)

The fact that the Staff will likely issue the SER serially, over several years, requires a different approach to scheduling discovery and hearings than would be appropriate if the entire SER were available in April 2010, as contemplated by Appendix D. Few non-NEPA contentions can be adjudicated before relevant portions of the SER are issued. To proceed expeditiously and efficiently, therefore, the Board believes that discovery and hearings should proceed serially as well.

 

April 4, 2008

SURFACE TRANSPORTATION BOARD ADOPTS PROCEDURAL SCHEDULE FOR DEPT. OF ENERGY APPLICATION TO BUILD 300-MILE RAIL LINE IN NEVADA

The Surface Transportation Board (Board) announced that it has adopted a procedural schedule concerning the United States Department of Energy's (DOE) application seeking authority to construct and operate an approximately 300-mile railroad line in Nevada in the Board proceeding entitled United States Department of Energy—Rail Construction and Operation—Caliente Rail Line in Lincoln, Nye, and Esmeralda Counties, NV, STB Finance Docket No. 35106.


To be known as the Caliente Line, the proposed rail line would connect an existing line near Caliente, NV to a proposed geologic repository at Yucca Mountain, in Nye County, NV. The proposed line would allow DOE to transport spent nuclear fuel and high-level radioactive waste for disposal at the proposed geologic repository, and to provide common carrier rail service to communities situated along the proposed line.


The Board's review of rail-line construction applications is governed by Section 10901 of Title 49, United States Code (49 U.S.C. 10901), and by the requirements of the National Environmental Policy Act of 1969 (42 U.S.C. 4321-4370d) and related environmental laws. Section 10901 requires that the Board grant a construction application unless the agency finds that a proposal is inconsistent with the public convenience and necessity. Because the DOE application is extensive and replies to it may be numerous, the Board finds that the standard construction-application timetable is inappropriate. Accordingly, the Board has established a longer schedule that will provide all parties ample time and opportunity for the submission of comments. The schedule also will better enable the agency to determine whether the proposed construction meets the criteria of Section 10901.


The Board published its Notice of Construction and Operation Application and provided a procedural schedule in its decision today, April 11, in STB Finance Docket No. 35106. That decision is available for viewing and downloading, via the agency's Web site at http://www.stb.dot.gov, under "E-Library," then under "Decisions & Notices," beneath the date "4/11/08."

The procedural schedule is as follows:

April 16, 2008

Publication of Federal Register notice adopting procedural schedule.

April 28, 2008

Due date for certification by DOE that it has published newspaper notices announcing this procedural schedule.

May 7, 2008

Due date for notices of intent to participate as a party of record (i.e., official participant)July 15, 2008: Due date for comments in support of or opposition to the application.

August 29, 2008

 

Schedule for the Licensing Proceeding on Consideration of Construction Authorization for a High-Level Waste Geologic Repository.

schedule

Schedule part 2

Schedule for the Licensing Proceeding on Consideration of Construction Authorization for a High-Level Waste Geologic Repository(After SER is Issued)

schedule part 2

Historical timeline - Key dates in the development of the proposed Yucca Mountain Nuclear Waste Repository

1954  The Atomic Energy Act is passed by Congress directing the federal government to promote the peaceful use of atomic energy, with the understanding that disposal of the highly radioactive waste produced would be the responsibility of the federal government.

1956  The National Academy of Sciences recommends deep geologic disposal of the long-lived, highly radioactive wastes from nuclear reactors, suggesting that buried salt deposits and other rock types be investigated for permanent repositories.

1960  In the early 1960s, the Atomic Energy Commission (AEC) announces that a salt mine at Lyons, Kansas, will be developed as a high-level radioactive waste repository, only to reverse its decision after state geologists discover the site is riddled with abandoned oil and gas exploration boreholes.

1975  The Energy Research and Development Administration (formerly AEC) begins to search for a possible permanent repository for the nation's nuclear waste. A multiple site survey emphasizing buried salt deposits and federal nuclear facility sites is conducted in 36 states, including Nevada, but is reduced in scope due to decreased funding and political opposition from states.

1980  Deep geologic disposal is selected by the Department of Energy (formerly ERDA) in an Environmental Impact Statement as the preferred alternative for permanent disposal of commercial high-level nuclear waste.

1982  Congress passes Nuclear Waste Policy Act of 1982 (NWPA) which establishes a repository site screening process; requires two repositories to assure regional equity; sets a schedule leading to federal waste acceptance for disposal beginning in 1998; starts the Nuclear Waste Fund to pay for the waste program with fees collected on the generation of electricity from nuclear power plants; and requires that the repositories be licensed by the Nuclear Regulatory Commission.

1983  The DOE names nine previously screened potential repository sites in six states: seven in salt deposits and two on western federal nuclear facility sites (including the Nevada Test Site) in volcanic rock deposits. Critics claim the sites were recycled from the 1975 search, and that the NWPA requires DOE to conduct a new screening process rather than proceed with sites considered prior to the passage of the NWPA. DOE slows down its process to involve the states and federal agencies in a more consultative process.

1986  The DOE issues final Environmental Assessments and nominates five candidate repository sites from the original nine, and then selects three western sites -- in Nevada, Texas, and Washington -- for detailed investigation, from which one is to be selected for repository licensing.

1986  The DOE indefinitely postpones the second repository siting program, violating the regional equity intent of the Nuclear Waste Policy Act, after much objection from states in the northern mid-west and east where potentially acceptable repository sites in granite are prohibited.

1987  Congress amends the NWPA, designating Yucca Mountain, Nevada as the sole repository site to be characterized. Two other sites are removed from consideration, the screening process for a second repository site is ended, and studies of repository sites in granite are prohibited.

1988  DOE holds public hearings on their site characterization plan for Yucca Mountain.

1991  Surface studies begin at the Yucca Mountain site

1993  DOE begins grading work on first phase of the Exploratory Studies Facility at the proposed repository site. DOE also formulates a new Program Approach that sets waste acceptance to begin in 2010, relies on DOE's development and distribution of Multi-Purpose Canisters to begin interim waste storage in 1998, sets a site characterization schedule which defers some work to a repository performance confirmation period lasting up to 100 years after waste emplacement begins.

1994  Portal entrance to the Exploratory Studies Facility is constructed and tunneling into Yucca Mountain begins. Critics charge that the portal ramps and entrance are constructed for use as a repository, not a study area.

1995  Tunnel boring machine makes progress into Yucca Mountain but encounters loose ground at various points. Five miles of tunnels are planned for the study area by 1996. Bills are pending in Congress that re-prioritize the waste program to emphasize interim waste storage and transportation, with site characterization as a lower priority.

1997  Thermal testing begins at Yucca Mountain. It is scheduled to take eight years.

1998  DOE fails to meet its January deadline for waste acceptance. Lawsuits are filed by states and the nuclear industry. Legislation that would put an interim storage facility on the Nevada Test Site dies in Congress. The Yucca Mountain Viability Assessment is released in December with DOE declaring the site "viable" but admitting that much work still needs to be done before the site can be officially recommended in 2001.

1999  Bills emphasizing interim spent fuel storage at the Nevada Test Site are again introduced in the US Congress with President Clinton vowing to veto any such legislation. The Draft Environmental Impact Statement for Yucca Mountain is released for public comment in August.

2000  Due to concerns that the EPA's role in setting radiation standards would be too limited, President Clinton again vetoes nuclear waste legislation passed by Congress. The site characterization project continues at Yucca Mountain as DOE prepares the Final Environmental Impact Statement and nears the point where suitability must ultimately be decided.

2001  EPA announces proposed radiation standards for Yucca Mountain. The State of Nevada files suit against the EPA, arguing the standards are inadequate. DOE is forced to investigate allegations of collusion between itself, its contractors, and the nuclear power industry to promote the repository. The release of the final Environmental Impact Statement is delayed until late 2001.

2002  Energy Secretary Spencer Abraham recommends Yucca Mountain as a suitable site to President George W. Bush. Bush approves the recommendation. Nevada Governor Kenny Guinn exercises the State's right to veto the Yucca Mountain project. The project moves to Congress, where a simple majority in both houses is needed to overturn Guinn's veto. Yucca Mountain is debated and passed first in the House of Representatives and then more narrowly in the Senate. President Bush signs the joint resolution into law, officially designating Yucca Mountain as the nation's nuclear waste repository site. DOE begins work on its application for a license to build and run the repository. The Nuclear Regulatory Commission (NRC) identifies 293 technical issues DOE must solve before submitting the license application. The State of Nevada files major lawsuits against DOE, NRC, Bush, and Abraham.

2003  DOE continues work on its license application to the Nuclear Regulatory Commission. The project, however, is over-budget and behind schedule. Nevada's lawsuits against the Yucca Mountain repository are set for oral arguments in front of the D.C. Court of Appeals in January 2004. DOE is scheduled to release a nuclear waste transportation plan sometime in the fall.

2004  The U.S. Court of Appeals in Washington, D.C. throws out the EPA's 10,000 year radiation standard for Yucca Mountain, but dismisses Nevada's other lawsuits. The Department of Energy selects the southern Nevada Caliente corridor to build a rail line for shipping waste to Yucca Mountain (Carlin is named the alternative). Nevada files suit over the Caliente Rail Line. An NRC Board rules that DOE's Yucca Mountain public internet database (Licensing Support Network) is incomplete. It is uncertain whether DOE will submit its license application to the NRC in December as planned. An NRC Comissioner and other officials say a 2010 opening is unlikely.
January 2005: Energy Department unveils plan for aboveground nuclear waste storage of up to 46.3 million pounds.

March 2005: Energy Department says U.S. Geological Survey employees may have falsified documentation on quality assurance work.

May 2005: Federal judge denies Western Shoshone's lawsuit against project. Tribe cites sacredness of Mother Earth and rights under the Ruby Valley Treaty of 1863.

July 2006: Energy Department sets schedule for submitting license application to NRC by June 30, 2008.

March 2007: Energy Department blames disgruntled former U.S.G.S. scientists, senior managers for document falsification. Says changes made.

October 2007: Energy Department issues environmental studies. Certifies license application document database complete.

December 2007: Nuclear Regulatory Commission panel rejects Nevada challenge to database. Congress cuts Yucca Mountain budget to $390 million in fiscal 2008, $104 million less than Bush requested.

January 2008: Chief contractor Bechtel SAIC lays off Yucca Mountain workers.

May 2008: Energy Department awards $13.8 million contract to two firms to design waste canisters.

June 3, 2008: Energy Department submits application to Nuclear Regulatory Commission for license to build, operate Yucca Mountain.
Sept 9, 2008: NRC decided to accept for review the Department of Energy's application to build the nuclear waste handling facility at Yucca Mountain, Nevada.
Hearings to begin sometime in 2009 - to be determined. New hearing panel of judges are being determined by the NRC's chief judge.