Yucca Mountain Project Update January 16, 2008
|
|
Presented to the Nuclear Waste Technical Review Board
|
|
E. F. Sproat - Director, Office of Civilian Radioactive Waste Management US DOE
|
|
Milestones
|
|
Design for License Application Complete - Nov 2007 - Actual: Completed 12/1/07
|
|
LSN Certification - Dec 2007 - Actual: Oct. 2007
|
|
Supplemental EIS - May 2008 - Actual: Draft Issued October 2007/Hearings completed
|
|
License Application Submittal - June 2008 - on schedule as of January 1, 2008 (impact of $108M FY 08 appropriations reduction currently being evaluated
|
Start nevada Rail Construction - Oct 2009 - delayed - inadequate funding to proceed with design |
|
YM Construction Authorization - Sept 2011 - Best achievable date
|
|
Operating License Submittal - March 2013 - predicated on funding and construction schedule
|
|
Rail Line Operational -June 2014 - 2016 is achievable only if adequate funding is provided
|
|
Begin Receipt - March 2017 (best achievable date) currently under evaluation due to FY 07 and 08 actual funding shortfalls - firm date can't be set until funding issue resolved
|